Orange Tree HOA – Ryan, Mason
December 6, 2021 @ 7:00 am - 3:30 pm
Materials have not been ordered, we can start with pulling wire for the new circuits, then get the materials to you.
Contract
South Entrance
Install new sub panel next to meter main combo, relocate existing circuits to new sub panel to make room for new sub panel breaker
Pull new circuits through existing conduits to allow for dedicated 20a/125v for each new sign on each side of entrance
North Entrance
combine circuits that can be done without conflict, then install new breakers
Pull new circuits through existing conduits to allow for dedicated 20a/125v for each new sign on each side of entrance
alternate (subject to approval)
Add 3 – GFI protected receptacles on tower for plug and play lighting installed by others. Feed from existing receptacle at base of tower on back side.