- This event has passed.
Hauff – Hayes Ragan – Vilmos, Tanner, Ben
December 20, 2021 @ 9:00 am - 3:30 pm
Contract
Materials on shop
Raise exterior porch light at game room entry to not conflict with exterior swinging storm door.
Install pool bath vanity light (vanity set and location marked on wall)
Move in-law side dining fixture to 48″ from west wall (materials from Grainger came in for this)
Install outlet for exterior water heater
Install outlet for two exterior A/C units.
Connect power for AHU
Check bath fans and make sure they are wired.
(all A/C equipment and exhaust fans to be set by 12.17.2021)
Install outlet for main kitchen range, cut sheet on site.
Final electrical panel schedule.
Install missing screws on interior main electrical panel (for outside corners)
Bring Temporary Pole back to shop
Water closet was supposed to have an outlet in it. Was one installed and covered by drywall?
Receptacles in bedroom #2 don’t work
Install blank cover on master bedroom fan
Install final lamps
Install kitchen island power. One outlet on side and outlet for dishwasher and disposal.
(after Nolette Lintel for Vilmos and Tanner, after Lepping for Ben)