Adams – Kemp Rough – Logan
March 22, 2022 @ 7:00 am - 3:30 pm
Get materials needed from shop first – service, arlington boards, ground screws, etc….
Contract
Rough Punch List
Ground Pancake boxes at coach lights
Build service
Add WP GFI at service
Chase low voltage down inside wall and stub out
Ground side door coach light
Missing receptacle on wall right of kitchen
Receptacle on front wall not on print (extra? written up)
Small appliance receptacle right of sink is past counter move to left inside pink line
Range receptacle goes in a 4″ square x 2 1/8″ metal boxes with a 2 gang metal ring turned sideways (mount flush in wall)
Receptacle to left of range isn’t on counter need to shift between pink lines
Switch legs and feed in/out need to be marked on wire above box (don’t worry about this one, moving forward need to be marked)
Second light junction in kitchen area (extra? written up)
Paddle fan in garage (extra? written up along with switch)
Receptacle required in bonus area on wall common to bedroom (GFI protect)
Light wire not secure rear door bonus area (can’t wait on framers)
Materials and low voltage wire still on job site (must be removed once rough is complete)
Complete wiring at shower (can’t wait on framers)
Complete 2 gang in bonus area by double door
Bonus area GFIs (are they set up to be GFI protected? supposed to be up at 44″ (we do 48″ I prefer) Why are they down low?
Fan in bonus area (extra? written up along with switch)
7:00am