Vogel – Lot 140 Trim – Ben, Gerard, Vilmos, Ethan
December 2, 2024 @ 7:00 am - 3:30 pm
Contract
Everything ready to finish
7:00am
Any questions get with Lauren or Vilmos, there is a punch list Lauren has (this may be it);
BC Lot 140 Update 11/11:
⁃ Detatched Gar
• Final schedule in pen (after lights are in)
⁃ Gar
• Install appliance cord for WH, waiting on install
⁃ Entry
• Coach lights not working (troubleshoot when all lights installed)
⁃ Kit
• Waiting on backsplash install to flush receps
• Re-install tape lighting when UC are put back up
• Cooktop hookup, waiting on install (will need 3/4” greenfield and #6 wire)
⁃ Bath 6
• Install 1 vanity light
⁃ Master
• Sitting light came with wrong bulbs- 4 candelabra
⁃ Master Clo
• Install recep in island (not installed yet)
⁃ Lights Missing:
• Gar Coach lights- 5
• Puck lights- 14 (with 3 (60w) drivers)
• Pool bath- 2 pendants
• Lanai- 1 fan
• Bed 6- 1 fan
• Hallway by master/suite 6- 1 clo strip light