
Contract
Finish rough
Inspection scheduled
After house is ready for inspection, Josh M. go on to your job….
Need service built and conduit stubbed for SECO past A/C Pad along with well conduit tied in to meter main
Print walk house make sure nothing got missed
Make trim list complete with breakers needed
7:00am
Posted in