- This event has passed.
Bella Collina – Justin G., Josh M., Logan, Chris
February 14, 2022 @ 7:00 am - 3:30 pm
Contract
***Priority***
J Drewes – Lot 297 Slab – MUST BE DONE FIRST THING – Justin G., Chris
Materials on site, book and print in office, LAYOUT ON PRINT MAY BE WRONG, Add panel pipe service right (between windows, you’ll see UFER ground), panel to be on wall in garage behind bathroom. We can cut the block at the man door leading from garage to house and 45 it right there to get where we need to be. They will be a chase so we need to be just outside of the block wall in the garage. The island pipe is in by another contractor. The A/C equipment conduit we will stub straight out from panel to left side of house.
J Drewes Lot 299 Slab – MUST BE DONE AFTER 297 – Justin G., Chris
Same service and panel layout, needs island conduit and A/C equipment conduit.
HBH – Volheim Lot 137/138 – As Needed
**************
Contract
HBH – Lot 444 Punch Out – Hold waiting on HBH
HBH – Lot 98 Rough – Logan, Chris (finish punch list after slabs)
Vogel – Lot 147 Rough – Josh M., Justin G.
HBH – Lot 75 Trim – As Needed
Vogel – Lot 145 Trim Extra – Waiting on puck transformer
Time and Materials
LHP – Lot 444 Pool – Did we ever wire the interior pool controller?
7:00am