Derelle – Wall Rough – Justin H., Tanner

July 26, 2021 @ 7:00 am - 3:30 pm

Contract

Finish rough for inspection if not already done.

Supposed to call for underground locates before digging.

Complete underground. Must expose power feed, water line, and phone/CATV lines before digging with machine. Need line from power to new garage. Need conduit from building to gate for power 3/4″ should be big enough. Do not dig in easement with machine near roadway.

(after shop)

If time left we could use your help with the machine you borrowed at Little Brownie Properties (LBP) with Brandon.

Need to run conduit between light poles. This job has already had underground locates completed. Or if we can keep the machine for Tuesday we could do this job then.