- This event has passed.
Hauff – Hayes Slab/Temp – Dustin, Paul
May 19, 2021 @ 8:00 am - 11:00 am
Need to convert two underground t poles to overhead
Contract
Materials in shop
Get the book and print and make sure you have everything you need before going out to site.
Temporary, overhead with 2″ conduit up the side. Location staked, doesn’t require bracing, make sure no open KOs, no breaker openings, devices WR, in use covers “extra duty” or “heavy duty”, one ground rod, all receptacles must be GFI protected or disconnected and wire nutted off.
(after Smith)