Moore Properties – Dustin
June 12 @ 8:00 am - 10:00 am
Contract
Materials in shop
Tags on outgoing job shelf
Protect GEC running on surface with sch 80 conduit
Phase ground wire green where ever it appears in a cabinet, box or visible
Install tags marking main and where interior is fed from. Install tag marking fault current
Check with office to make sure we have every issue listed here and didn’t miss any
(After Ferguson)