Contract
312 power is on, all A/C, A/H, and sump pump from both houses are wired and ready to go.
312- Facing into garage, the left two fluorescent lights need adjustment. Hanging slightly down from ceiling.
312- Waiting on heights for kitchen pendants, dining chandelier, entry chandelier, and master sitting chandelier.
Waiting on kitchen cabinets and summer kitchen cabinets.
312- The office floor box was missed by tile guys. They put hole in wrong spot and covered the floor box.
312 – Need hot check.
(After LBP)