Hauff – Aronoff Trim – Dustin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

Contract Materials in shop Per failed inspection; Relieve stucco 1/4" space along bottom of meter main (Garett spoke to Larry and he will accept bottom being cleared on stucco to allow water shed) Install intersystem bonding block (per photo I have its there, just needs to be cleared to get cover off and make it…

Hauff – Aronoff Trim – Dustin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

No power to the water heater Failed final inspection GFI‘s in the laundry and upstairs bathroom inspector states not GFI protected 7:00am

Hauff – Aronoff Trim – Dustin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

Contract Finish everything 7:00am Per Garett; Living: install missing receptacle Kitchen: install two gain cover plate Install plug for warming drawer Stairs: Install three candle lights Cover plate missing screw Outside: Exposed wires on back eve There might be one or two other things feel like I’m forgetting something but I’ll be there tomorrow morning…

Hauff – Aronoff Trim – Dustin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

Time and Materials Move receps for range down Plugs must be below 5.25 inches 7:00am

Hauff – Aronoff Trim – Tanner, Dustin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

Contract Adjust island conduit and pull wire make up complete. Find Microwave wire Garret to meet to assist with island cabinet removal 7:00am

Hauff – Aronoff Trim – Justin

Hauff - Aronoff Remodel Lockbox 2002 1875 Settle St., Clermont, Fl.

If it passes inspection, they want it tied in and turned on (do on the way back to the shop)