LBP – Bldg 4 Power Tie In – Ryan, Tanner

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Door Code 9653 Time and Materials Materials in shop (wire and taps) Linda has arranged outage Bldg 4 (Shop) will be off and bldg 2 will be open between 7-7:30am to confirm 7:00am

LBP – Rick, Ryan, Ben, Tanner

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials Materials in shop (I’m grabbing) Building #4 sub panel Exterior wall packs Scissor lift on site 7:00am

LBP – Bldg 7 – Ben

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials relocate conduit the way she wants it now. anything else pressing for rough, but we have the other appointment to get to. 7:00am

LBP – Bldg 7 – Ben

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Conduit Change how conduit is run (after Nolette)

LBP – Bldg 7 Demo/Rough – Ben

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials (after Notarantonio)

LBP – Bldg 7 Demo/Rough – Ben

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials Clean up existing electric (delete the old plastic boxes and romex and see if you can eliminate the up high junction boxes.) Rerough as is same number of receps and switches. 1 LED low bay fixture for each office and then four more out in open area. You’ll need 12 - 4”…

Little Brownie Properties – Dustin

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials Materials in shop once delivered Tuesday morning from Besco 3:00pm

Little Brownie – Dustin

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Well pump not working $145/h + material 7:00am

Little Brownie – Dustin

Little Brownie Properties 1350 Sheeler Ave., Clermont, Fl., FL, United States

Time and Materials Lights behind building 11 stay on 24/7 7:00am